Final Taking-Over Certificate for Hermosillo cement plant in Mexico

Beginning of 2008, Holcim Apasco awarded Fives FCB with a contract for the engineering and supply of a complete 3,500 tpd cement plant located in Hermosillo, Mexico. After the successful commissioning of the plant in 2010 and its inauguration in March 2011, in the presence of the President of Mexico, Felipe Calderon, the Final Taking-Over Certificate was signed by Holcim Apasco and Fives FCB on 14th of June 2012.

This cement plant features the latest technologies developed by Fives FCB to reduce energy consumption of the plant:

Following the successful completion of the Cartago 3,000 tpd complete plant in Costa Rica in 2004, this new project attests of the Holcim group's satisfaction and confidence in Fives FCB innovative technologies.