Bayano grinding plant, Cemex (Panama)

Bayano_Horomill_grinding_plant
  • Grinding plant capacity: 120 tph
  • Contract date: November 2006
  • First cement production: January 2008


In 2006, Cemex awarded Fives FCB with a contract for the turnkey supply of a cement grinding plant in Panama, in order to increase its production capacity. The contract was signed in two steps:

  • July 20th, 2006: Mechanical equipment
  • November 3rd, 2006: implementation of the grinding plant on an EPC basis

In order to answer the huge cement demand in Panama, Cemex decided to increase the production capacity of its Bayano cement grinding plant and entrusted Fives with the turnkey supply of a FCB Horomill® grinding plant on an EPC basis.

The FCB Horomill® grinding technology has been selected for its low energy consumption and the short delivery time proposed by Fives to supply the equipment.
The Horomill® grinding plant has been delivered 1.5 months ahead of the contractual schedule and the first cement produced 16 months after the signature of the EPC contract.

In its Bayano plant, Fives supports its client in operations and maintenance for the Horomill® grinding plant through a yearly technical services agreement.


Contact us

Fives FCB

Head Office
Sales Department

France

Phone: + 33 3 20 43 75 01
Fax: + 33 3 20 43 75 13


Brazil

São Paulo

Phone: + 55 11 4195 3098


India

Chennai

Phone: + 91 44 4292 7272
Fax: + 91 44 4292 7282


Russia

Moscow

Phone: + 7 495 745 5647
Fax: + 7 495 775 4840